PARKED STAIR-V1 — 2026-09-28. Preserved planning history. V1-PROOF now governs active work.
Checklist: mechanical release before the actuator set#
2026-09-28: no components purchased. Current eight-axis stair design rejected. See head and leg review. Checked research work does not mean hardware has passed.
- Audit prior head dimensions, CoM assumptions, single-support claims, vendor ratings and BOM.
- Produce candidate H1 front/side/plan allocations and itemized mass/inertia model.
- Run 91-sample full-step screening with real yoke/axle offsets; record failed compact cases and the 26-inch connected candidate, including 810 interpolation checks and explicit limitations.
- Decide support mechanism: finite-width tire contact plus controlled ankle, or leveled positively locked landing shoe. Show the real ankle orientation/load path.
- Decide compact 24-inch target versus explicit taller alternative; tire envelope, track and roll travel follow the mechanism.
- Validate a timed full-step path with the real ankle mechanism in both support directions; extend the sampled 26-inch result. Both feet end on the upper tread; no clamped IK or instantaneous height changes.
- Check swept head/frame/housings/knees/treads/links/fasteners/cables/springs against one another and the actual stair/nosing.
- Select real battery and boards; confirm nominal fit, connectors, cable bends, cooling, removal and restraint.
- Verify head mass/COM/inertia and per-link mass with measurements; keep contingency separate.
- Size mounted stationary and dynamic joint duty, reductions, spring curve, external bearings and structural fatigue/deflection.
- Validate carbon layup, tube cuts, sockets and bond/pin coupons. Old Sheet 2 cuts/springs are not released.
- Full-size nonpowered mockup clears the entire articulation before motor commitment.
- Restrained one-leg rig: 10-second controlled support, ±10 mm COM uncertainty, defined disturbance and controlled return, both sides.
- Mounted thermal duty and torque-speed/current at battery minimum; loss-of-power support and hardware catch.
- Only then release the remaining motor set, fabricate the second leg and begin 9/10 complete-step trials.
Historical Sheets 1/2 exist and count as past 2D study, not approval for manufacturing a redesigned leg. COTS spars, service access, draft-friendly customs and deliberate internal wire paths remain requirements.