HUXMechanical project
WorkshopParts & budgetV1-PROOF · R05 current build

V1-PROOF / Engineering project

Parts & budget

Recorded orders, remaining purchases and the original cost allowances.

PT / V1

PT-01 / Procurement ledger

Orders & remaining purchases

$195.94 recorded spend · $704.06 remaining in the $900 plan, with reserves.

Detailed budget & shopping list ↗

$195.94 recorded spend (Pololu $88.34 + Waveshare servos $54.78 + Pico/IMU order $30.58 + step-down converters $8.47 + servo board $13.77). The Pico 2, the LSM6DSO IMU and the servos are received. One more wheel gearmotor, one more driver and the wheels are necessary. $704.06 remains in the $900 plan. Read the remaining shopping list ↗

Original planning caps · $900 with reserves
V1-PROOF cash allocations including reserves
AllocationCap
Total planned ceiling$900

PT-02 / Component register

Parts & availability

Received, ordered and unconfirmed parts remain distinct from tested hardware.

Full inventory →

See the published inventory for recorded quantities and availability.